Improving
Overall Performance at Palisades Nuclear Plant
A CRI Success Story
By Andrew J. Pullam, Senior Technical Instructor, Nuclear
Management Company
Palisades Nuclear Plant is one of six nuclear plants operated
by Nuclear Management Company (NMC). Under NMC’s business
model, each plant owns and markets the power produced by
its nuclear unit. However, through NMC, employees from all
sites are able to collaborate to improve operational performance
and sustain long-term safety and reliability levels across
the six plants. Recently, NMC accepted the challenge of improving
the operational performance and reliability of two installed
reciprocating Instrument Air Compressors at the Palisades
Nuclear Plant.
Palisades Nuclear Plant was experiencing extensive equipment
downtime and rework due to poor maintenance practices. For
example, in three critical areas, the plant’s performance
failed to meet established criteria.
Performance
Area |
Performance Criteria |
Actual Performance |
| Downtime for periodic maintenance over a rolling 12-month
period |
438 hours |
More than 1200 hours |
| Functional failures over a 12-month period |
Less than 3 |
More than 6 |
| Percentage of time compressors are available for operation |
Greater than 95% |
86% |
NMC conducted analysis to identify the specific trends that
would need to be addressed during the next training cycle.
They found that the existing maintenance and repair training
for the air compressors was general in nature and did not
focus on the current performance needs of the organization.
They also found that many of the technicians had not completed
any type of refresher training even though the availability
of the two compressors fell significantly below the established
performance criteria.
The results of the analysis revealed a need to enhance the
existing training and focus specifically on improving the
overall performance of these compressors. To do this, NMC
redesigned the compressor training using the Criterion-Referenced
Instruction (CRI) methodology.
During the course design and development process, NMC identified
and corrected many procedural and material deficiencies.
They also made significant changes to the way the training
was delivered.
The previous training program consisted of an 8-hour course
conducted at a training center followed by an on-site, on-the-job
(OJT) evaluation that took approximately 5-6 days to complete.
Scheduling the OJT to coincide with the plant’s maintenance
schedule proved next to impossible. This had significant
repercussions on training. For example, in one OJT session,
27 technicians needed training to learn how to perform a
specific maintenance task. However, only 6 to 8 technicians
(those with the most experience) actually had the opportunity
to perform the task on the equipment due to the sensitivity
of the equipment to plant operations. This meant that only
about 25 percent of the technicians were qualified to perform
the task after completing training.
After implementing the CRI methodology, training time totaled
32 hours. This included ample opportunity for learners to
practice their newly learned skills on an exact replica of
a compressor (purchased specifically for training purposes
at a cost of $30,000). The cost of the replica compressor,
however, is more than offset by the performance improvements
resulting from the CRI-based training course.
CRI Training Results
After completing the new training course, all of the technicians
successfully demonstrated competence in all of the areas
associated with the maintenance and rebuild of the compressors.
The increase in fully trained technicians has produced
the following impressive results:
Performance
Area |
Performance criteria |
Actual Performance |
Rate of Performance Improvement |
| Downtime for periodic maintenance |
438 hours |
Less than 400 hours |
Reduced actual downtime by 67% and exceeded performance
criteria by close to 10% |
| Functional Failures |
Less than 3 |
Less than 4 |
Reduced actual failure rate by 50%; reduced the gap
to meet performance cirteria by close to 70% |
| Availability of compressors |
Greater than 95% |
96% |
Increased compressor availability by 12% and exceeded
performance cireteria by 1% |
In addition to these performance improvements, Palisades
has also:
• Saved in excess of $800,000 in air compressor replacement
costs
• Reduced average repair time from 5-6 days to approximately 28 hours
Most importantly, use of the CRI methodology has provided
the framework for bolstering self-confidence (or self-efficacy)
of the workforce through demonstrated task performance. This
boost in self-efficacy has enabled the workforce to identify
and correct additional equipment deficiencies before they
become significant operating liabilities.
Andrew Pullam currently serves as a Senior Technical Instructor
with Nuclear Management Company. Originally from East Alton,
IL, Andrew retired from the US Navy in October 2001 after
serving 20 years in the Naval Nuclear Power Program as an
operator and technician. While in the military, he earned
a Bachelor of Science Degree in Workforce Education Training
and Development from Southern Illinois University. In May
2001, he was selected by the Charleston Regional Business
Journal as one of the "Top Forty Under 40" in recognition
of outstanding leadership in the Charleston Business Community
as a Training and Professional Development Consultant. Andrew
recently completed CEP’s Expert
Course Manager Workshop,
which certifies him to teach the Criterion-Referenced
Instruction Workshop throughout Nuclear Management Company.
|